Description
The TriMet capstone project team designed a cut and cover box for a LRT line for TriMet. This project includes the reinforced concrete design of the box along with an in-depth construction plan, project schedule, and estimate. The two semester project addressed the alternatives and design/planning sections of the project.
Citation: Pilot Scholars Version (Modified MLA Style)
Alindogan, Logan; Diaz-Gunning, Emily; Manke, Alec; and Soares, Emily, "TriMet - LRT Grade Separation using a Single or Double Barrel Reinforced Concrete Cut and Cover Box" (2020). Engineering E-Portfolios and Projects. 53.
https://pilotscholars.up.edu/egr_project/53

Project Information
CE 483 – Civil Engineering Capstone Project I
CE 484 – Civil Engineering Capstone Project II
2020 Shiley Showcase Presentation